Capital Improvement

About the Capital Improvement Program

The Engineering Division serves as the lead in the preparation of the City's Capital Improvement Program and budget submitted for City Council consideration. After City Council approval and authorization is obtained, the division proceeds with the preparation of bid documents and subsequent performance of contract administration and inspection of these projects.

HOME DEMOLITION AT 107 E 2ND AVENUE - PROJECT 1-D-23

This Project will demo the existing property at 107 E. 2nd Avenue for a future public parking lot.

TIMELINE:
Demolition Construction: 4/26/2023 - 5/2/2023

STATUS:
This project will start April 26, 2023. Residents near the project will receive a notice letter in front of their doorstep on April 20, 2023, with information about the project and contact information. Below is a copy of the notice:
LAhabranotification English and spanish

ANNUAL SEWER REHABILITATION PROGRAM, MAIN SEWER LINING FY 2021-2022 & 2022-2023 CITY PROJECT 1-S-23:


This project will involve relining the existing 8" and 12" sewer lines at Dexford Drive from Story Avenue to Wilshire Avenue and Ashley Circle from Hillandale Avenue to the cul-de-sac.

Timeline:
8" Sewer Lining construction: 5/04/2023 - 5/04/2023
12" Sewer Lining construction: 5/12/2023 - 5/12/2023

Status:
The project will start on May 3, 2023, by cleaning the pipes, and on May 04, 2023, the sewer relining begins. Residents near the project will receive a notice letter in front of their doorstep on May 8, 2023, with information about the project and contact information. Below is a link of the Public Notice (English/Spanish).

OLD RESERVOIR PARK LANDSCAPE & LIGHTING REDESIGN

The Old Reservoir Park is currently being redesigned for new landscape, lighting, and security cameras; new trees will be planted to provide fall colors and abundant shade throughout the year, and additionally a variety of accent plants and low spreading plants will keep the park beautiful.  The walking path will be upgraded to decomposed granite and new Miracle Play and fitness equipment will be spread throughout the park - the equipment, available fro all ages to use - is perfect for families and friends to enjoy.  A shade structure, tables, benches, and drinking water fountains will accommodate the proposed outdoor equipment and new lighting will keep the park illuminated for security purposes, while deflectors will keep the light to a minimum from the neighboring houses.  Lastly, the existing pump station currently at the park will be removed in the new future, but for now, the fascia surrounding the station will be upgraded with screen plants as to be more aesthetically pleasing. 

Proposed Project Milestones: 

  • Final Design - January 2022
  • Construction - Summer 2022

Concepts: